*Note: This particular schedule was for a simple 1000 sq.ft. home… this is a perfect scenario schedule. Winter construction and weather will affect/delay the timeline. The schedule listed is just to help homeowners understand the approximate sequence and process of building their home. A schedule is flexible so homeowners should not be surprised if their particular home does not follow this exact order.* Week 1:
Footings ![]() Week 2:
Waterproofing the Block Backfill
Week 3 and 4:
Week 5:
Heating, Plumbing & Electrical Rough-ins
![]()
![]() Week 6:
Temp. heat to thaw basement (winter construction) Insulation Drywall
Week 7:
Soffits and Facia Brick/Stone ![]() ![]() Week 8:
Trimwork Cabinets installed Concrete floors are poured ![]() ![]() ![]() Week 9:
Countertops installed
Week 10:
Ceramic tile installed Laminate wood flooring installed Heating, Plumbing & Electrical finishes ![]() ![]() ![]() Week 11:
Trimming finish Driveway installed Garage doors installed Siding ![]()
Week 12:
Carpet installed Final Clean Final Grade ![]() Week 13:
Final Paint Landscaping Final Walk through ![]() ![]() Week 14:
Mortgage lender inspections Week 15:
![]() |